HUB Update
The HUB is looking great! We are still tracking toward an October substantial completion date for the exterior and an overall project completion date in December. Pictured (on 8/21) is the front exterior, windows installed on the east side, decking being installed on the west side, and interior work for the Student Life offices. Over the next couple of weeks, windows will continue to be installed, decking will be finished, and exterior finishes on columns will begin. Also, the perimeter fencing has been retracted with the new sidewalk being finished, so feel free to walk by to check out the activity and progress!